A pilot can only pass if "pass" was written down as numbers before the first job ran, and the same document should say what passing triggers: how many full racks are held for you, for how long, at what configuration and price, and what either side may do if the pilot fails or a date moves. Agree four things before the pilot starts: measurable acceptance criteria, a capacity hold you can exercise by notice, a validity period for the configuration and the price, and exit terms. GMI Cloud takes GB300 NVL72 on pre-order through our sales team, and commitment options are agreed in that same conversation, so a buyer can table all four terms alongside the reservation request. More broadly, GMI pricing lets workloads move from on-demand to dedicated or committed deployments as they stabilize, without being pushed into a long-term commitment too early.
Without these terms, a successful pilot leaves procurement with a good engineering report and still no claim on a rack, no agreed rate, and no date.
Each criterion needs a metric, a threshold, a measurement method, and a named person who records the result. The thresholds below are placeholders to show the format; yours come from your own capacity plan.
| Area | Metric | Example threshold (assumed) | Recorded by |
|---|---|---|---|
| Functional | Agreed job list runs end to end on the pilot trays with the pinned image | Every listed job completes | Customer |
| Throughput | Tokens or samples per second per GPU at fixed batch size and precision | At least 90% of the per-GPU figure in the capacity plan | Customer, with provider witness |
| Latency, for inference | p95 time to first token at the target concurrency | 800 ms or less at 64 concurrent sessions | Customer |
| Stability | Continuous run on the pilot trays | 72 hours with no hardware-caused interruption | Both sides |
| Data path | Checkpoint restore time or dataset read rate | Restore within 10 minutes | Customer |
| Operations | A support request handled through the agreed process | Opened, acknowledged, and closed as the support terms describe | Both sides |
Four details keep the table from turning into a dispute later.
The acceptance report is only useful if each possible result has a contractual consequence agreed in advance.
| Outcome | Customer position | Provider position | Next step |
|---|---|---|---|
| Pass | May reserve the held racks within the exercise window | Keeps the racks held until the window closes | Reservation signed on the pre-agreed terms |
| Fail, provider-side cause | No obligation to reserve | Fixes the cause, retests, and extends the hold by the retest time | Rerun the failed criteria |
| Fail, workload-side cause | No obligation to reserve | Hold lapses at the end of the window | Re-scope, for example a different rack count, or stop |
| Inconclusive | Pilot extended | Pilot trays and hold extended together | Finish the remaining tests |
The line between provider-side and workload-side causes is where disagreements start, so agree beforehand on the evidence that settles it: the hardware and fabric logs the provider will share with you, the provider's incident records, and your own job logs on the same timeline. A throughput miss from a failing GPU and one from an untuned input pipeline look alike in a summary table and very different in the logs.
A sales note that says full racks are "expected to be available after the pilot" records intent. It gives the provider nothing to hold and gives you nothing to exercise. A capacity commitment names a quantity, a hold period tied to the acceptance date, a way to exercise it, and what happens if you don't.
Here is an example of a clause a buyer can propose for the contract. It is a drafting sample, not GMI's standard terms.
Example clause: "Provider will hold two (2) GB300 NVL72 racks for Customer from the pilot start date until thirty (30) days after the Acceptance Date (the Hold Period). The Acceptance Date is the day both parties sign the pilot acceptance report, whether it records a pass or a fail, or, if no report is signed, fifteen (15) days after the scheduled pilot end date. A provider-side retest, or a pilot extension agreed for an inconclusive result, extends the Hold Period by its length. Customer may reserve the held racks by written notice during the Hold Period, on the term, rate, and configuration set out in Schedule B. If Customer gives no notice, the hold ends without charge."
A right of first refusal works differently. It gives you priority when another buyer makes an offer, and unless the clause says more, it sets nothing aside before that happens. A fee or deposit doesn't strengthen a hold by itself either. The strength sits in what the clause obliges: whether named capacity is reserved for you, whether you can exercise without further consent from the provider, whether the provider may withdraw, and what happens to any fee on each outcome in the table above, including racks that can't be delivered. If a fee applies, the contract should also say whether it is credited against the reservation or can be applied to other usage when the pilot ends without a reservation.
A pass on one configuration says little about a different one, so the reservation should describe the same system you piloted. Attach a configuration manifest at pilot end covering the system, the host architecture, the software baseline, the access model, the fabric type, the storage tier, and the region. Any change between pilot and rack, such as a different driver baseline or a different site, should trigger a rerun of the criteria it affects.
Price needs the same treatment. Schedule B should state the committed rate together with the term it assumes and keep both valid until the hold period ends, because the rate depends on that term: GMI pricing prices on-demand and committed usage differently. The fabric and storage lines that come with the racks need their own rates and the same validity date in that schedule. Leave them out, and a held rack can arrive with a compute rate that held and a storage line that moved.
A worked timeline makes the dates concrete. Assume a four-week pilot that starts in week 1. The acceptance report is signed in week 5, the 30-day hold runs to roughly week 9, and the reservation signed inside that window carries its own delivery window and acceptance test for the racks. If the report stalls, the clause's fallback date starts the 30 days anyway.
Delivery clauses for any Blackwell reservation, such as slip notice and remedies, apply here as usual. A pilot-to-rack path adds a few items of its own.
Once the pilot passes, the workload team hands procurement a package that lets the reservation be signed without reopening technical questions.
Two engineers who watched the tests run, one from your workload team and one from the provider, should sign the measured values. A commercial owner on your side then signs the decision to exercise or not. Splitting the signatures keeps the technical record separate from the buying decision, which helps if the hold or retest terms are ever questioned.
They can, through a written amendment both sides sign before the affected test runs. A threshold changed after a result is known turns the pilot into a negotiation. If your capacity plan shifts mid-pilot, update the plan, re-derive the threshold, and amend the criteria before rerunning.
Bring the rack count you expect to reach, a draft of your acceptance criteria, and the dates your project depends on. With those in hand, our sales team can discuss GB300 NVL72 pre-order and commitment options against your own pass mark, so the pilot result has a clear place to land. Contact GMI Cloud sales to start the conversation.